CONSTRUCTION START:  March 2019
CONSTRUCTION END: May 2019
COST: $480,000
PROJECT PHASE: Complete
RESTORATION: Pending
100%

Project Description

Shawnee Mission Parkway MapAs our infrastructure continues to age, we proactively replace water mains to ensure safe, reliable, high-quality water service to our community with superior service. WaterOne will be upgrading infrastructure along Shawnee Mission Parkway from Mission Road to Neosho Lane, and Neosho Lane south of Shawnee Mission Parkway. WaterOne's work is scheduled to begin in March 2019 and last until May 2019. 

This project is being coordinated with KDOT and the City of Fairway. Portions of Shawnee Mission Parkway may be closed during working hours, but every effort will be made to maintain access and reduce disruption for commuters and residents. Please obey all posted traffic controls and detours. We appreciate your patience as we complete this necessary upgrade to your water infrastructure.

To be informed of water outages, please sign up with www.NotifyJoCo.org or call 913/826-5555. You can customize your contact preferences by tagging locations of your home, work, school, etc.