Water Main Replacement - Nieman Rd, Shawnee Msn Pkwy to 55th St

Print
Press Enter to show all options, press Tab go to next option

WaterOne Project Manager
 Kiel Johnson
(913) 895-5767

CONSTRUCTION START:  December 2018
CONSTRUCTION END: April 2019
COST: $825,000
PROJECT PHASE: Under Construction
RESTORATION: TBD
40%

Project Description

Nieman Road_Mapboard_3As our infrastructure continues to age, we proactively replace water mains to ensure safe, reliable, high-quality water service to our community with superior service. WaterOne will be upgrading infrastructure along  Nieman Rd from Shawnee Mission Parkway to W 55th St. WaterOne's work is scheduled to begin in December 2018 and last until April 2019. 

There is expected to be single-lane closures near the work zone during construction. Brief water outages of four hours or less will also be necessary, and all outage updates will be sent through NotifyJoCo.org. Every effort will be made to maintain access and reduce disruption for residents in this area. We appreciate your patience as we complete this necessary upgrade to your water infrastructure.

To be informed of water outages, please sign up with www.NotifyJoCo.org or call 913/826-5555. You can customize your contact preferences by tagging locations of your home, work, school, etc.


Updates will continue to be sent out via NotifyJoCo. Make sure your account is up-to-date at www.NotifyJoCo.org. You can also follow our progress at waterone.org/projects.