Water Main Replacement - 91st St, Roe to Mission

Print
Press Enter to show all options, press Tab go to next option

WaterOne Project Manager
Kirk Culbertson
(913) 895-5768

CONSTRUCTION START:  October 2018
CONSTRUCTION END: January 2019
COST: $360,000
PROJECT PHASE: Complete
RESTORATION: Spring 2019
100%

Project Description

91st StreetAs our infrastructure continues to age, we proactively replace water mains to ensure safe, reliable, high-quality water service to our community with superior service. WaterOne will be upgrading infrastructure along 91st Street from Roe Ave to Mission Rd. WaterOne's work is scheduled to begin in October 2018 and last until January 2019. 

Every effort will be made to maintain access and reduce disruption for residents in this neighborhood. We appreciate your patience as we complete this necessary upgrade to your water infrastructure.

To be informed of water outages, please sign up with www.NotifyJoCo.org or call 913/826-5555. You can customize your contact preferences by tagging locations of your home, work, school, etc.


Updates will continue to be sent out via NotifyJoCo. Make sure your account is up-to-date at www.NotifyJoCo.org. You can also follow our progress at waterone.org/projects.