WaterOne Project Manager
Kiel Johnson
Phone: 913-895-5767
Email Kiel Johnson
Project Description
As our infrastructure continues to age, we proactively replace water mains in conjunction with City projects to ensure safe, reliable, high-quality water service to our community with superior service. WaterOne will be upgrading infrastructure along Granada Street from 59th Street to 63rd Street. WaterOne's work is scheduled to begin in August 2018 and last until November 2018.
Every effort will be made to maintain access and reduce disruption for residents in this neighborhood. We appreciate your patience as we complete this necessary upgrade to your water infrastructure.
To be informed of water outages, please sign up with Notify JoCo webpage or call 913-826-5555. You can customize your contact preferences by tagging locations of your home, work, school, etc.
Updates will continue to be sent out via NotifyJoCo. Make sure your account is up-to-date at Notify JoCo website. You can also follow our progress at WaterOne Projects.
Project Update
- Construction Start: August 2018
- Construction End: November 2018
- Cost: $440,444
- Project Phase: Complete
- Restoration: TBD