WaterOne Project Manager
Kirk Culbertson
Phone: 913-895-5768
Project Description
As our infrastructure continues to age, we proactively replace water mains to ensure safe, reliable, high-quality water service to our community with superior service. WaterOne replaced an existing 12 inch cast iron pipe (1960 to 1966) with 16 inch PVC water main along Switzer Road between 91st Street and 95th Street. This project was in coordination with the City of Overland Park Street and Storm Sewer Improvement Project, which began August 2014. WaterOne's work began October 2014, and this project was completed in March 2015.
Project Update
- Construction Start: October 2014
- Construction End: March 2015
- Cost: $700,000
- Project Phase: Completed