Water Main Replacement - 91st Street, Roe to Mission

WaterOne Project Manager

Kirk Culbertson
Phone: 913-895-5768
Email Kirk Culbertson

Project Description

Water Main Replacement - 91st Street, Roe to MissionAs our infrastructure continues to age, we proactively replace water mains to ensure safe, reliable, high-quality water service to our community with superior service. WaterOne will be upgrading infrastructure along 91st Street from Roe Avenue to Mission Road WaterOne's work is scheduled to begin in October 2018 and last until January 2019.

Every effort will be made to maintain access and reduce disruption for residents in this neighborhood. We appreciate your patience as we complete this necessary upgrade to your water infrastructure.

To be informed of water outages, please sign up with Notify JoCo webpage or call 913-826-5555. You can customize your contact preferences by tagging locations of your home, work, school, etc.

Updates will continue to be sent out via NotifyJoCo. Make sure your account is up-to-date at Notify JoCo website. You can also follow our progress at WaterOne Projects.

Project Update

  • Construction Start: October 2018
  • Construction End: January 2019
  • Cost: $360,000
  • Project Phase: Complete
  • Restoration: Complete