Project Description
As our infrastructure continues to age, we proactively replace water mains to ensure safe, reliable, high-quality water service to our community with superior service. WaterOne will be upgrading infrastructure along Roe Avenue from 63rd Street to 67th Street. The project is coordinated with the City of Prairie Village to be completed before scheduled road improvement work, in order to avoid unnecessary excavation and maximize ratepayer dollars. WaterOne's work is scheduled to begin in April 2019 and last until May 2019.
Road closures will be necessary on Roe only during working hours of 8 am to 3 pm, beginning Monday, April 15th. New street crossings will be installed within the neighborhood affected and detours will be posted. We appreciate your patience as we complete this necessary upgrade to your water infrastructure.
To be informed of water outages, please sign up with Notify JoCo webpage or call 913-826-5555. You can customize your contact preferences by tagging locations of your home, work, school, etc.
Updates will continue to be sent out via NotifyJoCo. Make sure your account is up-to-date at Notify JoCo website. You can also follow our progress at WaterOne Projects.
Project Update
- Construction Start: April 2019
- Construction End: May 2019
- Cost: $100,000
- Project Phase: Complete
- Restoration: TBD