WaterOne Project Manager
Dana Williams
Phone: 913-895-5732
Email Dana Williams
Project Description
As our infrastructure continues to age, we proactively replace water mains in conjunction with City projects to ensure safe, reliable, high-quality water service to our community with superior service. WaterOne will be upgrading 7,950' of infrastructure throughout the neighborhoods between High Drive and State Line, from 73rd Street to 75th Street:
- Eaton St - W 73rd Street to W 75th Street
- High Dr - W 73rd Street to W 74th Terrace
- W 73rd Street - High Dr to State Line Road
- W 73rd Terrace - High Dr to State Line Road
- W 74th Street - High Dr to State Line Road
- W 74th Terrace - High Dr to Eaton St
WaterOne's work is scheduled to begin in October 2018 and last until Spring 2019.
Every effort will be made to maintain access and reduce disruption for residents in this neighborhood. We appreciate your patience as we complete this necessary upgrade to your water infrastructure.
To be informed of water outages, please sign up with Notify JoCo webpage or call 913-826-5555. You can customize your contact preferences by tagging locations of your home, work, school, etc.
Updates will continue to be sent out via NotifyJoCo. Make sure your account is up-to-date at Notify JoCo website. You can also follow our progress at WaterOne Projects.
Project Update
- Construction Start: October 2018
- Construction End: May 2019
- Cost: TBD
- Project Phase: Complete
- Restoration: Pending