WaterOne Project Manager
Eric Maassen
Phone: 913-895-5719
Email Eric Maassen
Project Description
As our infrastructure continues to age, we proactively replace water mains to ensure safe, reliable, high-quality water service to our community with superior service. WaterOne will be upgrading infrastructure throughout the neighborhoods between Broadmoor St and Riggs St, from 55th Street to 57th Street WaterOne's work is scheduled to begin in August 2019 and last until August 2020.
WaterOne will make every effort to maintain access and minimize disruption for residents for the duration of the project. Construction will only take place during normal working hours, Monday through Friday. Please watch for detours, equipment, and crews in the area. We appreciate your patience as we complete this necessary upgrade to your water infrastructure.
To be informed of water outages, please sign up with Notify JoCo webpage or call 913-826-5555. You can customize your contact preferences by tagging locations of your home, work, school, etc.
Updates will continue to be sent out via NotifyJoCo. Make sure your account is up-to-date at Notify JoCo website. You can also follow our progress at WaterOne Projects.
Project Update
- Construction Start: August 2019
- Construction End: August 2020
- Cost: $775,000
- Project Phase: Complete
- Restoration: 3rd Quarter 2020