Project Description

  • The new tower is a Composite Elevated Tank design, similar to other WaterOne elevated tanks in the service area.

To address customer demand needs identified in WaterOne's 2015 Master Plan Update, WaterOne is preparing to construct an elevated tank (water tower) near the intersection of highways K7 and K10 in Lenexa, KS. The two million gallon elevated tank will help meet future service needs. Construction of the new tank will ensure consistent water pressure, improve distribution system efficiency during periods of peak demand, and continue to guarantee the highest level of fire protection for WaterOne customers.

The new tower will resemble existing WaterOne elevated tanks located at 107th and Renner and 199th and Lackman. The project is expected to begin in Winter 2020 and will be completed by Summer 2021. Construction of the elevated tank will have no adverse impact to water service for residents nearby or in any other part of the system.

Updates will continue to be sent out via NotifyJoCo. Make sure your account is up-to-date at Notify JoCo website. You can also follow our progress at WaterOne Projects.

Project Update

  • Construction Start: Winter 2020
  • Construction End: Summer 2021
  • Cost: $5.6 Million
  • Project Phase: Complete