Water Main Replacement - 75th Street & Quivira Road

WaterOne Project Manager

Jesi Lay
Phone: 913-895-5720
Email Jesi Lay

Project Description

As our infrastructure continues to age, we proactively replace water mains to ensure safe, reliable, high-quality water service to our community with superior service. WaterOne will be replacing 510 linear feet of 8" distribution main and 270 LF of its 30" Quivira Transmission Main at the intersection of 75th Street and Quivira Road This work is being completed in advance of the City of Shawnee's 75th Street Corridor Capital Improvement Project. The work will take approximately 3 weeks to complete. The full closure of the intersection will be during Spring Break to reduce disruption to local schools. Restoration will be completed in conjunction with the City of Shawnee CIP. Please watch for detours, equipment, and crews in the area. We appreciate your patience while this necessary work is completed.

Traffic Impacts:

  • Single lane closures on eastbound and westbound 75th Street (Planned March 7-9)
  • Southbound Quivira Road lane closures (Planned March 9-13)
  • Full closure of 75th Street and Quivira Road intersection (Planned March 14-20)

To be informed of water outages, please sign up with Notify JoCo webpage or call 913-826-5555. You can customize your contact preferences by tagging locations of your home, work, school, etc.

Updates will continue to be sent out via NotifyJoCo. Make sure your account is up-to-date at Notify JoCo website You can also follow our progress at WaterOne Projects.

Project Update

  • Construction Start: March 2022
  • Construction End: April 2022
  • Cost: $330,000
  • Project Phase: Complete
  • Restoration: Spring 2022