WaterOne Project Manager
Kirk Culbertson
Phone: 913-895-5768
Email Kirk Culbertson
Project Description
As our infrastructure continues to age, we proactively replace water mains to ensure safe, reliable, high-quality water service to our community with superior service. WaterOne will be upgrading infrastructure in the neighborhood along Newton Street from 55th Terrace to Johnson Drive. The work will take approximately 3 months to complete. The project is being completed in conjunction with the City of Overland Park's planned street and stormwater project in order to reduce excavation and disruption to residents.
Please watch for detours, equipment, and crews in the area. We appreciate your patience while this necessary work is completed.
To be informed of water outages, please sign up with Notify JoCo webpage. or call 913-826-5555. You can customize your contact preferences by tagging the locations of your home, work, school, etc.
Updates will continue to be sent out via NotifyJoCo. Make sure your account is up-to-date at Notify JoCo website. You can also follow our progress at WaterOne Projects.
Project Update
- Construction Start: March 2022
- Construction End: May 2022
- Cost: $350,000
- Project Phase: Complete
- Restoration: Spring 2022