Bonner Springs; Kansas City, KS/Wyandotte County Project MP-05321 60 Transmission Main, Water Treatment Plant to Parallel Parkway. BRB Contractors, Inc., continues to install pipe. Approximately 4,,750 linear feet of a total of 27,950 linear feet of pipe have been installed. The project is approximately 20% complete. The contract substantial completion date is April 15, 2009. WaterOne Project Manager Mark Sunderson, 913-895-5757 Project MP-05322 60 Transmission Main, Parallel Parkway to Kansas River Tunnel. Garney continues site preparation. Construction has begun on the emergency interconnect with BPU and the surge facility structures. Pipe installation is expected to begin in February. Construction is approximately 8% complete. The contract substantial completion date is February 16, 2009. WaterOne Project Manager Rod Perry, 913-895-5767 Project MP-06009 60 Well Water Transmission Main, Collector Wells to Water Treatment Plant. BRB Contractors, Inc., continues to smaller pipeline installation and electrical duct bank work. Installation of the 60 pipeline is anticipated to begin late summer or early fall of 2008. Construction is approximately 12% complete. The contract substantial completion date is July 15, 2009. WaterOne Project Manager Mark Sunderson, 913-895-5757 Johnson County Project MP-05252 36 Transmission Main, 175th Street, Lackman Road to Ridgeview Road. Design continues to progress and geotechnical investigations are expected to begin in February. Additional details will be provided as the design progresses and a schedule for construction has been established. WaterOne Project Manager Jan Hardie, 913-895-5775 Overland Park Project MP-09003 - 20 Transmission Main, Nall Avenue from 151st Street to 159th Street. This project is being constructed in conjunction with the City of Overland Parks street improvement project along Nall from 143rd Street to 159th Street. Miles Excavation continues to work on the tunnel at 151st Street & Nall. Once the tunnel is complete, the 20 main will be installed. Construction is approximately 90% complete. WaterOne Project Manager - Brian Schade, 913-895-5766
|
|
||
|
|
Shawnee Project MP-05323 60 Transmission Main, Kansas River Tunnel to Receiving Tanks & Pumping Station (77th & K-7). Garney continues site preparation work and tunneling work. Pipe installation is expected to begin in February. Construction is approximately 10% complete. The contract substantial completion date is October 15, 2008. WaterOne Project Manager Rod Perry, 913-895-5767 Project MP-05324 - Kansas River Tunnel. Southland Contracting, Inc. has completed both the north vertical shaft and the south vertical shaft. Work on the horizontal portion of the tunnel is anticipated to begin in February. Construction is approximately 34% complete. The contract substantial completion date is December 15, 2008. WaterOne Project Manager Dave Flipse, 913-895-5765 Project MP-06008 24 Transmission Main, 71st Street, Clare Road to Hedge Lane Terrace. Design is approximately 90% complete. WaterOne has started the easement acquisition process. It is anticipated that the project will be advertised for bids later this spring. Additional details will be provided as the construction schedule is established. WaterOne Project Manager Carla Horn, 913-895-5773 |
||