Water Now Flowing to Western Lenexa
The City of Lenexa and WaterOne are pleased to announce completion of a 12” water main project that has made water available to the area west of K-7 Highway. The pipeline runs along Prairie Star Parkway, from Monticello Road to Mize Road, and south from Mize Road to K-10 Highway. The pipeline project was accomplished through a cooperative effort and agreement between the two governmental entities. In accordance with the agreement, WaterOne funded installation of a 54” tunnel under K-7 at a cost of approximately $400,000 and the City of Lenexa provided funding for the water main installation at a cost of a little more than $1 million through a special improvement district along the route of the pipeline. Property owners along the route will pay for the cost of improvements through a special assessment. The project was completed under budget. Construction on the project began in February 2004, and the pipeline was put in service July 2004.
|