For residential and commercial projects where the
developer wants the pipe to be installed across the proposed streets
prior to curbs and paving (street crossings), call Paul Harris,
Supervisor of Construction Inspection, at (913) 895-1888 to schedule
street crossings after the sanitary and storm sewers are installed and
subgrade elevation is established. Street crossing installation will
require the developer to furnish appropriate grade and alignment
stakes. The following site conditions must be established prior to the
installation of water mains: |
- Residential and commercial projects require
all sanitary and storm sewers to be in place. The water main will be
given priority for installation before all other underground
utilities are installed.
|
-
Where the water main is to be installed back of
curb, all curbs and pavement must be in place with curbs notched
with property line locations prior to scheduling the water main
installation. The ground surface within the proposed water main
alignment must be within 6 inches of final grade.
|
-
Where water main is under paving, ground surface
must be within 6 inches of final grade. All surface obstructions,
such as construction materials and equipment, within the
construction zone of the water main alignment must be removed.
|
-
For construction coordination and scheduling of
new main extensions or if you have any questions, please call Paul
Harris, Supervisor of Construction Inspection at (913) 895-1888.
|