following action was taken at the Board Meeting on February 10, 2009.
REVISIONS TO RULE
V, SECTION 5
The Board approved
revisions to Rule V. Section 5, Paragraph D of WaterOne’s Rules &
Regulations regarding trip charges related to discontinuance/restoration
of water services.
PURCHASE OF FACILITY 1 SERVICE PUMPS
The Board approved the purchase
of Facility 1 High Service Pump Nos. 3 & 6
replacements for Job No. AC-09919 from Letts, Van Kirk & Associates, in
the amount of $326,132.00.
AWARD OF CONTRACT FOR PROJECT MP-09008
The Board awarded a
contract for Project MP-09008, Installation of Kansas
Presed Traveling Screen No. 4 to
Foley Company, in the amount of $40,300.00.
ACQUISITION OF
EASEMENTS
The Board adopted a Resolution authorizing acquisition of easements by
Eminent Domain near Johnson Dr.
& K-7 for Project RA-08004, a 12” Main
Relocation.
CHANGE ORDER NO. 1 FOR PROJECT MP-05324
The Board approved Change Order
No. 1 for Project MP-05324, Kansas River Tunnel, allowing a reduction in
retainage from $667,636.10 to $150,000.
CHANGE ORDER NO. 6
The Board approved Change Order
No. 6 for Projects MP-05322 & MP-05323, which increases the contract
amount by $177,801.54, and extends the contract time by two days.